Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

You are developing strategies to effectively engage stakeholders throughout the project life cycle. What is the process you are working on?

A.Plan Stakeholder Management

B.Identify Stakeholders

C.Manage Stakeholder Engagement

D.Control Stakeholder Engagement

user-image
Question added by Nader Ali , Technical office manager , AlSafwa Contracting
Date Posted: 2016/08/18
KINGSLEY NWANKWO
by KINGSLEY NWANKWO , Project Procurement Manager , Lavie Energy Limited

On or before the  project kicks off, Procurement Department must engage all the Stakeholders involves in the project planning and execution, in other to access their. Input, Output, Tools and Techniques in.1. Identify Stakeholder [Input, Output, Tools and Techniques]2. Plan Management [Input, Output, Tools and Techniques]3. Engagement management [Input, Output, Tools and Techniques]4. Control Engagement [Input, Output, Tools and Techniques] etcThese entire highlightwith more can be accomplished through regular Project Management Team PMT meeting.

 

 

Umair Farooqi
by Umair Farooqi , Manager Technology Sourcing , Scotiabank

Procurement planning phase requires the commitment and engagement of stakeholders. It is at this process we identify what is being purchased, have we got funds, is it in the budget, what route we want to take, what is our existing stage and most importantly what we will achieve out of the project. All these questions needs to be answered in option A and B.

Ramiz Ismajli
by Ramiz Ismajli , Procurement Officer , Mabetex group

C..Manage Stakeholder Engagement-  with strategy development how to engage stakeholders you on the same time you managing their investment  and  the chances are that you can increase those investments too.

 

BHARAT JINGAR
by BHARAT JINGAR , EA CUM PROJECT MANAGER , SELF CONTRACTED

Person who has raised this question, must tell what is goal and objective otherwise stop it.

Nader Ali
by Nader Ali , Technical office manager , AlSafwa Contracting

Plan Stakeholder Management is the process to develop strategy to effectively engage stakeholders throughout the project life cycle.

More Questions Like This