Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

You are in process of exterminating which set of project activities will take the longest to complete? See below for detail

Which of the following is the MOST appropriate tool to use?

A. RBS

B. Gantt chart

C. WBS

D. Milestone chart

E. Network diagram

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/08/20
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

The most appropriate option is

E. Network diagram

Deleted user
by Deleted user

A Gantt chart, commonly used in project management, is one of the most popular and useful ways of showing activities (tasks or events) displayed against time. 

More Questions Like This