Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

If Contractor fails to fulfill QA/QC requirements on a project, what project management team will take decision against contractor?

A) Project Management Team will request the Client to terminate the Contractor.

B) Project Management Team will instruct the Consultant/Engineer to issue NCR against the Contractor's works to make sure QA/QC requirements.

C) Project Management Team will deduct some percentage(%) from Contractor's Monthly progress Invoice.

D) Project Management Team will warn the contractor and allow him to continue works to complete project on time.

 

 

user-image
Question added by Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia
Date Posted: 2016/08/27
Ihab Zaki
by Ihab Zaki , Chief Technology Officer (Cto) , EGID

B Project Management Team will instruct the Consultant/Engineer to issue NCR against the Contractor's works to make sure QA/QC requirements.

Deleted user
by Deleted user

Thanks for invitation -

They follow D - C - A Step by Step    !!!

Attia Emad
by Attia Emad , Electrical engineer , Advanced Vision for E/M works

B-Issuing an NCR by the consultant/Engineering (The authorized PM by the sponsor and customer) and circulate the appropriate incharges depts.(Procurements and financial) to deduct a monthly percentage amount of the contractor monetary funding  (funding requirements to complete project objectives)  based upon the contractual and legal obligation on the agreements and the list the contactor in the non-prequalified vendors. By the way there is a sum lump money allocated for the project's formal closure can deduct a certain amount if the vendor failed to meet the customer final requirements and expectations based upon the legal binding relationship .

Ammar Fadhil
by Ammar Fadhil , Civil Quality Engineer , Zain - Iraq

make B,D,C and A respectively. 

Pulak Mandal
by Pulak Mandal , Analyst , Accutest research laboratory

they first audit as for sop,and if it not full filled than they can take carrect stape for taht,agenst that .

 

Ashutosh  ranjan
by Ashutosh ranjan , NDT INSPECTOR , Bekem infra project pvt ltd

IT WILL GOOD TO FOLLOW THE PLAN B

Deleted user
by Deleted user

Project Management Team will deduct some percentage(%) from Contractor's Monthly progress Invoice.

Syed Shan Haider
by Syed Shan Haider , Senior Draftsman , Al Marwan General Contracting Company

i am agree with experts...........

 

Vahdat Moradi
by Vahdat Moradi , Supervision engineer of gas and petrochemical projects , Supervision engineer of gas and petrochemical projects

Project manager, resource manager, implementation manager and quality control manager

Faysal Shahzad
by Faysal Shahzad , manager university club , punjab university

calculate the cost and impose panalty on contractor.

JONES JOY
by JONES JOY , Mechanical Project Engineer , Generic Engineering Technologies

1. The project management team, including quality control inspectors, engineers, and project managers, identifies the QA/QC deficiencies.

2.We need to document the non-compliance, including photographs, test results, and witness statements.

3.A formal notification is sent to the contractor detailing the specific issues and required corrective actions.

4.The contractor is expected to respond to the notification within a specified timeframe, outlining their proposed corrective action plan.

5.This plan should include details on how the non-compliance will be rectified, the timeline for completion, and any additional resources required.

6.If the plan is deemed satisfactory, the contractor is allowed to proceed with the corrective actions.

7.The final decision-making authority rests with the project owner or client.

8.If the plan is satisfactory and the contractor successfully implements it.