Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

You are a project manager for a company that sells online music. Your project is to develop new content management system that will not only manage?

 

all users purchases and downloads but will automatically learn the users music interest to make future product recommendation. In addition your content management system must scale to support millions of current music downloads a

day. Your team has made a significant progress on the project. You are preparing the performance of the project to date and have calculated the following measurement:

PV=, EV=, AC=

What is the CPI of the project?

A.0.

B.1.

C.0.

D.1.

E.1.

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/08/28
Imran Ahmed
by Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia

CPI COst Permance Index = Earned Value/Actual Cost =EV/AC

EV=AC

CPI=EV/AC=EV/EV=1

Answer Option-B,D & E

CPI = 1 means that the cost of completing the work is right on plan (good)

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Thanks for the invitation.

Answer is B ,D & E - 1.

When PV = EV = AC , CPI has to be 1 only .

ANKESH KUMAR
by ANKESH KUMAR , ISO Management Consultant , Excelledia Quality Consulting

Sure, If the risks have been addressed and severity is been controlled and it is to be monitored on regular basis.

Thukaram Jogi
by Thukaram Jogi

Yes, by implementing the Standard Operating Procedures of the Organisation and adherence to quality policies of the Organisation. Thus attaining sustainability in the market

Muhammad Imran Mahar
by Muhammad Imran Mahar , Plant Inspector In Inspection department , Engro polymer&Chemical LTD Port Qasim Karachi Pakistan

Yes My company is not allowed the music in work area

More Questions Like This