Register now or log in to join your professional community.
all users purchases and downloads but will automatically learn the users music interest to make future product recommendation. In addition your content management system must scale to support millions of current music downloads a
day. Your team has made a significant progress on the project. You are preparing the performance of the project to date and have calculated the following measurement:
PV=, EV=, AC=
What is the CPI of the project?
A.0.
B.1.
C.0.
D.1.
E.1.
CPI COst Permance Index = Earned Value/Actual Cost =EV/AC
EV=AC
CPI=EV/AC=EV/EV=1
Answer Option-B,D & E
CPI = 1 means that the cost of completing the work is right on plan (good)
Thanks for the invitation.
Answer is B ,D & E - 1.
When PV = EV = AC , CPI has to be 1 only .