What's the method statement for insulation (Mineral Fibre) for chilled water pipes?

user-image
Question added by Muhammad Arsalan Siddiqui , Associate Director (MEP) , JLL
Date Posted: 2016/08/29
Mohammed marwan
by Mohammed marwan , Mechanical Engineer , Al Tiraq Trading & Contracting WLL

For Chilled Water supply Pipe we don't need to use mineral Fiber because glass fiber insulation is enough for chilled water pipe in order to protect from physical contact only  

Mohammed Shebl
by Mohammed Shebl , Contracts Manager , SALFO - Engineering & Management Consultants

1- cut pipe insulation longitudinally according pipe length 2- apply adhesive in inner of insulation 3- apply adhesive on pipe 4- put the insulation in pipe and make pressure by your hand in places to remove any air lock between insulation and pipe 5- apply adhesive tape over the longitudinal seem