How to calculate the Labor, equipment, shuttering & rebar for 1 M³ concrete as per UAE market ?

user-image
Question added by ARUN K VIJAYAN , Quantity Surveyor Engineer , Dhabi Contracting
Date Posted: 2016/08/31
dafallah hamadalneil
by dafallah hamadalneil , project engineer , ELRACE CONST. BUILDING CONTRACTNG

we can divide it to 2 things

1- material

2- labour charge

material means :1- concrete price and that depend of wat element u want to cast it sub or super struc. and is it required green concrete or SRC or OPC approxmately it will be around AEd255 if its green concrete

oAed 215 if it SRC for mix 400 kg grade 40 n

also pump charge will be assume 50/m3

2- reinforcement depend of the element u will cast it and also the building itself

but usually we use 100-90 kg/m3 for isolated footing

and for slabs 100-110 kg/m3

180-160 kg/m3 for colomns

3- accessories like binding , nails and curing assume Aed for each

4-labour charge assume it Aed 250 /m3

5-plywood and wood assume it Aed 120/m3

6-scaffolding 15/m2

7- profits around 50-40% of cost

ELMER LIMPIADO
by ELMER LIMPIADO , Civil Engineer , Mauritius For Trading & Contracting Ltd.

...get the total volume of works with respect to the type of concrete works they are are doing, i,e. slab, foundation, columns, etc. Calculate every forms and scaffolding needed in the constructions, the number of labors required to do the job including supervisors and the equipment which shall be utilized in the process. It must be done in detailed. Provide costs in every estimated labors, forms and scaffolding and equipment. If the total cost, i.e labor+equipment+shutterings+rebars+concrete, are tabulated, divided it with the total volume in order to get the per unit cost. I have no idea how much the cost of Labor, equipment, etc. in UAE - I am in KSA but basically this is the processes.

Shoaib Ismail Ismail
by Shoaib Ismail Ismail , Project Forman , Elbaz

Helloe how I calculate footing wood shutteing square meters 

Muhammad Faheem
by Muhammad Faheem , Model Engineering & Contracting CoDubai

TO CALCULATE THE COST OF BUILDING CONSTRUCTION WORKS FOLLOWING ARE THE CATEGORIES

1. MATERIAL 

2. MANPOWER

3. TOOLS & EQUIPMENT 

4. PERMIT REQUIRED FOR CONCERNED ACTIVITY

5. LOSSES 20% 

6. MARKUP (PROFIT)

How can calculation the cost analysis for each activity for construction project in UAE , So I need some one teach me (not for free ) . My email is

Osama Setohy MCIOB
by Osama Setohy MCIOB , Senior Quantity Surveyor , Keo International Consultants - Qatar

The prices are different from country to another, but we are using the same way to build the prices as per standard method of measurements.

for concrete, it's different from grade to another and calculated by cubic meter

for rebar, it's different from size to size and wether its coated or not and calculated by Kg.

for shuttering, it's different from element to another (column, footing, beam, slab .. etc.)and calculated by square meter.

for Labor, equipment and profit, they are included in all of the previous prices as per company's standard prices and percentage.