to finish on time. The number of resources is written into the contract. What’s the BEST way to proceed?
A. Your project will be late because you can’t change the contract once it’s signed
B. You need to convince the buyer to sign a new contract
C. You need to use the contract change control system to make the change to the contract
D. You need to use claims administration to resolve the issue
when there is a delay in delivery - when the cost is high compared to other sources - when the material supplied is out of specifications or not genuine-
The customer desire to add more resources means he didn't commit to the conditions of the contract since the resources are already mentioned and agreed on. Accordingly a change in the terms/conditions of the contract must be applied
Thanks for the invitation.
Option C is the answer. Change control system is used to make changes to the contract that is in progress.
Option-C
You need to use the contract change control system to make the change to the contract