Your company has just received approval to purchase a company that offers complementary services to your company. As PM on the acquisition, you?

develop a deliverable-oriented grouping of project elements that organizes and defines the total scope of the project. This output is called: A. Work Breakdown Structure

B. Scope Management Plan

C. Organizational Breakdown Structure

D. Scope Definition

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/09/13
Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

It is A - Work Breakdown Structure . WBS is a document that, as you have rightly said , a deliverable oriented grouping of project elements that defines total scope of the project.

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Looks Option (A) closed to Question 

Imran Ahmed
by Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia

Option-D Scope Definition................