Question added by Adel Amhawal , General Manager Operations , Barga for Construction
Date Posted: 2016/09/16
Imran Ahmed
by Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia

  • Very rapid speed of erection
  • Good quality control
  • Entire building can be precast-walls, floors,beams,etc.
  • Rapid construction on site
  • High quality because of the controlled conditions in the factory
  • Prestressing is easily done which can reduce the size and number of the structural members.

osama allam
by osama allam , Finance Manager , ELTorath for tourism Development Co. S.A.E

reduces the site labour componentdramatically, which in turn, reducessite costs and time.The erection crew, necessary forprecast construction, will usuallyconsist of only about 5-6 people,rather than the several dozen required   for in-site construction.

PROJECT DESIGN

QUALITY CONTROL

Short delivery time

 

Sattar Abdulkarim  Mohamed
by Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

Thanks for your invitation. I think the answers of our colleagues above are quite enough to meet and cover your question.

Mousab Al Nokkari
by Mousab Al Nokkari , Engineering Manager , Al Majaz Engineering Consulting Office

 

Thanks for invitation ,,

 

The concept of precast (also known as “prefabricated”) construction includes those buildings where the majority of structural components are standardized and produced in plants in a location away from the building, and then transported to the site for assembly.

 

These components are manufactured by industrial methods based on mass production in order to build a large number of buildings in a short time at low cost. The main features of this construction process are as follows:

 

·         The division and specialization of the human workforce.

 

·         The use of tools, machinery, and other equipment, usually automated, in the production of standard, interchangeable parts and products

 

Many countries used various precast building systems during the second half of the 20th century to provide low-income housing for the growing urban population.

 

They were very popular after the Second World War, especially in Eastern European countries and former Soviet Union republics. In the former Soviet Union, different precast buildings systems are denoted as “Seria,” whereas in Romania they are called “Secţiunea.”

 

In general, precast building systems are more economical when compared to conventional multifamily residential construction (apartment buildings) in many countries.

 

With Best Regards

Waleed Hamdy
by Waleed Hamdy , MEP PROJECTS CONTROL HEAD SECTION , AZMEEL CONTRACTING COMPANY

In typical buildings projects 

Ihab Zaki
by Ihab Zaki , Chief Technology Officer (Cto) , EGID

For many reasons like:

1- Quality control of concrete.

2- Reduction of construction time at site.

3- Better Project Management and more accuracy as there will be less dependency of weather conditions.

4- Ability to produce pre-stressed concrete easily at factory which can have a good impact on size and number of mainly beams.

Deleted user
by Deleted user

When :

1 - It is intended to double the pressure of concrete and iron resistance in the concrete element powers.

2 - It is intended to reduce the time period for the concrete structure.3 - It is intended to reduce the total cost of the project.

mamoun mokhtar
by mamoun mokhtar , general manager , albyan technical foungary

when we have very long boundaries to construct , wen the site is very far from ready mix plants or material sources are difficult to transport like cement ,water ,aggregate , when reduction of time of execution is considered , when we need quality job , when the cost is compromised, when we thinking of future shift of the site and claim precast concrete to be used again

Md Fazlur Rahman
by Md Fazlur Rahman , Procurement Specialist , Engineering and Planning Consultants Ltd

If  the design has been made taking into consideration the use  precast concrete for some element  and if you have the modern technology (high capacity crane and associated equipment, highly skilled workers), you may go for precast concrete construction. This is more suitable for large scale project as initial investment in equipment, machinery will be high.

Nader Ali
by Nader Ali , Technical office manager , AlSafwa Contracting

  • when we have big spans
  • When we need less time to finish the project

 

Mohammed Noser
by Mohammed Noser , Civil Engineer , aalbwardi.com

I am agreed with all answers  added but i think it is not suitable for parametric and organic or complex architectural design