Project risk is characterized by three factors, what are they?

   a-Severity of impact, duration of impact and cost of impact.

    b-Identification, type of risk category and probability of impact

   c- Risk event, risk probability and the amount at stake

  d-  Occurrence, frequency and cost

user-image
Question added by Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL
Date Posted: 2016/09/17
Imran Ahmed
by Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia

Option-C  Risk event, risk probability and the amount at stake

It is important to know the risk event that can take place, how much is it probably and what will be its impact if it occurs.

TARIG BABIKER AL AMIN
by TARIG BABIKER AL AMIN , Head of Planning and Studies Unit , Sudanese Free Zones and Markets Co.

Thanks for invite : Risk event, risk probability and the amount at stake - c - option

Nadjib RABAHI
by Nadjib RABAHI , Freelancer , My own account

The answer is :

Option C : risk event, risk probability and the  amount at stake

Ksenija Kancelak
by Ksenija Kancelak , Construction Project Manager , City of Koprivnica, Koprivnica (Croatia)

 I thing the right answer is: C 

DR MD ANWAR HOSSAIN
by DR MD ANWAR HOSSAIN , Moderator , bayt.com

Project risk is characterized by - 01. Identification, type of risk category & probability of impact.

02. Risk event, risk probability and the amount of stake.

03. Occurrence, frequency and cost.

( ------------    Option (C) Risk event, risk probability and the amount at stake      -------------)

sardar mardookhy
by sardar mardookhy , PMP certified Project manager , MCCI

Risk event, risk probability and the amount at stake,

thanks