A. Conflict over technical opinionsB. Conflict over schedule and costC. Conflict over personnel resourcesD. Conflict over personality issues
Reply -----------------------
Option-D is answer......................
Thanks for the invite.
It is D - Personality issues are always lowest source of conflict and that is how it should be.
Option D is appropriate choice as you have already made progress and there is little chance of personality issues. Personally issues, if any, that has been already solved by the competent project manager.
Thanks for your invitation. My Reply is Option D. Conflict over personality issues.
I thing the right answer is: D
D IS THE ANSWER,...
...............
Okay it could be very nice
Technical issue is the lowest source of cnflict
Option(D) Conflict over personality issues