Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

An accepted deadline for a project approaches. However, the project manager realizes only 75% percent of the work has been completed. (cont.)

The project manager then issues a change request. What should the change request authorize?

A. Additional resources using the contingency fund

B. Escalation approval to use contingency funding

C. Team overtime to meet schedule

D. Corrective action based on causes

user-image
Question added by Nader Ali , Technical office manager , AlSafwa Contracting
Date Posted: 2016/09/20
Nader Ali
by Nader Ali , Technical office manager , AlSafwa Contracting

The Answer is D. Corrective action based on cause

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Agreed with Krishna option and explanation

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Thanks for the invitation.

Project manager does not have to issue a change request to use contingency funds or call team meeting to speed up the schedule, because a PM is authorized through project charter to do both on his own.

In the given situation he just has to take ( D ) Corrective action based on causes.  

Imran Ahmed
by Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia

Option-D Corrective action based on causes,,,,,,,,,,,,,,,,,,,,

More Questions Like This