A. Correct the project manager's mistakes.B. Provide for answers for upper levels of managementC. To assess project status or progressD. To apprise the project costs and cost trends of the project
Thanks for the invite.
It is C - To assess project status or progress.
Option (C). To assess project status or progress
Performance reviews are held to to assess project status or progress.
Sure Option-C.......................................................................................