Which of the following statements are TRUE regarding various Activity Scheduling tools?

A. PDM allows for conditional branching and iteration of activitiesB. PDM uses activity-on-node (AON) diagramming method.C. PDM allows for conditional branching and iteration of activitiesD. PDM uses analogous methods as an estimation technique

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/09/25

Option (B) PDM uses activity-on-node (AON) diagramming method

Imran Ahmed
by Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia

Option-B, PDM uses activity-on-node (AON) diagramming method

 

PDM = Precedence diagram method

 

Nader Ali
by Nader Ali , Technical office manager , AlSafwa Contracting

My Answer is B uses AON method