Register now or log in to join your professional community.
A. generating ,gathering and disseminating information to formalize the phase or project complition.
B. collecting and disseminating performance information.
C. completing and settling conracts, including resolution of any open items.
D. both A and C
The answer is : Option D- both A and C
Option (D) Both A and C ---------------
The steps :
1- Knowing the reasons .... (+ yes or - no )
2 - Study contracts ..... (+ yes or - no )
3- Comparison of actual and theoretical costs .... (+ yes or - no )
4- Follow-up workers and working ..... (+ yes or - no )
5- Review project materials ..... (+ yes or - no )
6- Review schedules ..... (+ yes or - no )
7- Audit of the financial and moral benefits ...... (+ yes or - no )
Finally : it was +++ yes >>> --- no ... in this case must stop ,
Before that , my answer ( D )
..... Thanks .
These primary areas of the shutdown process are: • Personnel • Operational Capability/Requirement • Technology • Facilities/Hardware/Software/Program Security • Contracts • Budget
Thanks for the invite.
It is option C.
First thing to do before stopping a project is " completing & settling contracts including resolution of any open issues / items ".