Register now or log in to join your professional community.
simple as possible.What is not a method of reporting earned value?
A. Apportioned.
B. Milestone.
C. Level of Effort (LOE)
D. Varience analysis
Thanks for the invite.
Of course it is B - Milestone. Milestone has no time and cost attached to it.
My oppinion is that B is right answer.
Thanks for your invitation. Option- B.
I think milestone is good answer. Thank you.
My answer is option (B) -----------
Thanks for the invitation. I would like to select option B.
Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.