You are working through the initiation phase of your project for a new client that involves opening new operations in 3 new locations.

 Several of the functional managers have very different views on how the project should be managed and what the deliverable should be.As the project manager for this project for this project which of the following is the best thing for you to do?

A. Ask the client when they will be in agreement on project requirements.

B. Work with leadership from each area to collaboratively engineer a mutually acceptable solution.

C. Make sure the terms and conditions of the contract are very very clear especially how changes will be managed.

D. Advice the client they must reach agreement on both issues within2 weeks, Otherwise, the schedule have to be defferred until they are able to agree as a

 

 

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/10/08
Md Fazlur Rahman
by Md Fazlur Rahman , Procurement Specialist , Engineering and Planning Consultants Ltd

Answer: 

Option B. Work with leadership from each area to collaboratively engineer a mutually acceptable solution.

 

 

Deleted user
by Deleted user

Thanks for the invitation Sir! My answer is option B

mamoun mokhtar
by mamoun mokhtar , general manager , albyan technical foungary

decisions and alternations are always taken by total understanding and coordination with the concerned managers and engineers , i think the answer is B. Work with leadership from each area to collaboratively engineer a mutually acceptable solution.

Sattar Abdulkarim  Mohamed
by Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

Thanks for your invitation. Option B is a convenient answer in this case/ four choices.

DR MD ANWAR HOSSAIN
by DR MD ANWAR HOSSAIN , Moderator , bayt.com

My is also as like as above experts option -B.

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Thanks for the invite.

I will go with option B as it appears most appropriate of all.

Ksenija Kancelak
by Ksenija Kancelak , Construction Project Manager , City of Koprivnica, Koprivnica (Croatia)

My oppinios is that the right answer is B.