Your manager gives you a scope of work and asks you to begin work immediately and provide her with a schedule. What should you do first?

 

A. Begin estimating the task necessary to complete the scope of work.

B. Identify the stake holders and make sure their requirements are included in the scope of work.

C. Create an activity list and then begin to assign the task to resources.

D. Identify a team and obtain approval for their participation from their functional managers.

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/10/09
Sattar Abdulkarim  Mohamed
by Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

Thanks for your invitation. Option A.

Deleted user
by Deleted user

B. Identify the stake holders and make sure their requirements are included in the scope of work.

Mohamed Riyas A M PMP
by Mohamed Riyas A M PMP , Project Manager , Twozan Surveys

Begin work immediately and provide a schedule is what is asked for. In order to estimate schedule and start work, we need to first have work breakdown structure (WBS) created for the scope, and then define activities to accomplish the packages in WBS. So to me, the best option is A, i.e., to begin estimating the task necessary to complete the scope of work.

mamoun mokhtar
by mamoun mokhtar , general manager , albyan technical foungary

when the scope of work is defined already and you are going to execute then you should know what are your needs first i think option A. Begin estimating the task necessary to complete the scope of work. may be good answer

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Thanks for the invite.

In my opinion  it should to be option B first followed by option A .

DR MD ANWAR HOSSAIN
by DR MD ANWAR HOSSAIN , Moderator , bayt.com

I seem option  A- Begin estimating the task necessary to complete the scope of work.