Which of the following is not considered part of the quality control process.
A. quality audits.
B. continually monitoring process.
C. identifying and eliminating problem causes.
D. use of statistical process control to reduce process variability and increase effice
The answer is B) continually monitoring the process. Monitoring the process is one of the activities of quality assurance not quality control. In monitoring the process one approves the process not the deliverable of the process. And in Quality control we are concerned about the deliverable if it is accepted or not.
D id the correct answer. Process variability is not part of the quality control process
The answer is : Option C- Identifying and eliminating problem causes