A. It is the responsibility of the sales person in charge to identify all risks relatedto a customer project.B. Managing and organizing assumptions means avoiding risks right from the start of the project.C.Organizational, environmental and external assumptions should be addressed by the project charter.D.Risks are a sign of uncertainty. Avoiding all uncertainties means that a projectshould have no risks at all.
Option C
Organizational, environmental and external assumptions should be addressed by the project charter.
Thanks for the invitation. My answer is C
Thanks for the invite ............................c
Thanks for the invitation. Option C - Relevant answer for this question particularly during the initiating processes.
Thanks for invitation
Option C