What is typical for critical chain project management?

A. Management of buffersB. Management of total floats and free floatsC. Management of leads and lagsD. Management of resource over-allocations

user-image
Question added by DR MD ANWAR HOSSAIN , Moderator , bayt.com
Date Posted: 2016/10/12
hisham abu dagga
by hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

Option A

Thanks for invtation

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Thanks for the invite.

Of course it is D - Management of resource allocation.

Abdul Rehman
by Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thanks for the invitation. My answer is option A

Ihab Zaki
by Ihab Zaki , Chief Technology Officer (Cto) , EGID

A. Management of buffers

Project buffer, Feeding buffer and Resource buffer.

Mohammed Asim Nehal
by Mohammed Asim Nehal , M Asim Nehal & Co , Chartered Accountants

The correct answer is :

 A. Management of buffers                                                                                 