Register now or log in to join your professional community.
What is the earned value of the project? o $3,,o $3,,o $4,,o $5,,
Thanks for the invite.
Earned Value is the sum of CV + AC , i.e EV = 4,000,000 + ( - 500,000 ) = 3,500,000 $
The answer is EV = $ 3,500,000
Thank you for the invitation. The answer is $ 3,500,000
The Earned Value = 3500,000.00 $