Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

On an ad-hoc base, they had to find and implement a workaround to avoid delays and mitigate technical problems. What should you do next?

A. During execution in a project to build a major road bridge, your team found a major flaw in the technical drawings.  B. Meticulously document the problem and the workaround to create a requested change to the project management plan, which will then be passed to the body responsible for the change control decision.  C. The workaround was performed on a technical level only. As long as it does not influence the function of the bridge or the organizational configuration of the project, a change request will not be necessary.A retroactive formal change request side is not reasonable. Create some additional documents describing the workaround and sign them by yourself, you can present them during the next regular CCB meeting.  D.I t is normal in projects that during project execution inconsistencies arise between planning documents and actual implementation. This is no problemas long as the functional status of the product is maintained.

user-image
Question added by DR MD ANWAR HOSSAIN , Moderator , bayt.com
Date Posted: 2016/10/12
Basim Natour
by Basim Natour , General Manager , sulaiman alrajhi construction company

Would rather go with option B

Abdul Rehman
by Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thank you for the invitation. My answer is B

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Thanks for the invite.

I will go with Option C .

Since workarounds are unplanned responses developed to deal with the problems on the occurrence, they do not have to go through CCB before implementation.

More Questions Like This