Product acceptance criteria should be laid down in which document?

A.  Project scope statement

B.  Work breakdown structure

C.  Resource assignments

D.  Project scope management plan

user-image
Question added by DR MD ANWAR HOSSAIN , Moderator , bayt.com
Date Posted: 2016/10/12

Project scope management plan

hisham abu dagga
by hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

option A.

Thanks for invitation

Option (A) -------------------------------------

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Looks  A.  Project scope statement  ----------------

Abdul Rehman
by Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thank you for the invitation. My answer is option A

Ihab Zaki
by Ihab Zaki , Chief Technology Officer (Cto) , EGID

A.  Project scope statement

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Thanks for the invite.

Of course it is A - project scope statement 