Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

In cost monitoring, the s-curve depicts the relation between:

 

A. Schedule complition and time.

B. Cumulatives value and time.

C. Schedule complition and value resources.

D. resources and time

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/11/26
Sattar Abdulkarim  Mohamed
by Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

My answer is Option B - Cumulative value and time.

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

It is option B - Cumulative value & time and thanks for the invitation.

 

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Option B is most suitable answer ---------------------

More Questions Like This