Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Scope Verification is?

A) Performed at the end of project planning

B) Essentially same as quality control

C) Primarily concerned with acceptance of the work results

D) Primarily concerned with correctness of the work results

 

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/11/26
mamoun mokhtar
by mamoun mokhtar , general manager , albyan technical foungary

Scope verification is the process of formalizing acceptance of the project scope by the stakeholders (sponsor, client, customer, etc.). It requires reviewing work products and results to ensure that all were completed correctly and satisfactorily.

Sattar Abdulkarim  Mohamed
by Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

It is Option A - Scope Verification is performed at the end of the project planning.

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

It is C - Primarily concerned with acceptance of the work results and thanks for the invitation.

A) Performed at the end of project planning

Abdul Rehman
by Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thank you for the invitation. My answer is A