Work package is a?

 

A) Element at the lowest level of WBS

B) Task with unique identifier

C) Required level of reporting

D) Task that can be assigned to only one person

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/11/26
Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

My first choice is option B - Task with unique identifier . If option B was not given , I would have gone for option A.

Deleted user
by Deleted user

Elements required by  certain environment to fulfill the oriented Task.