Register now or log in to join your professional community.
• Most common technique for performance measurement.
• Integrates the project scope, cost, and schedule measures to assist the project management team to assess project performance from initiation through closeout.
• Involves calculating:
◦ *Planned Value (PV): The authorized budget assigned to scheduled work. It is also known as performance measurement baseline (PMB)/ budgeted cost of work scheduled (BCWS).
◦ *Actual Cost (AC): The realized cost incurred for the work performed on an activity during a specific time period. It is also known as actual cost of work performed (ACWP).
◦ *Earned Value (EV): The measure of work performed expressed in terms of the budget authorized for that work. It is also known as budgeted cost of work performed (BCWP).
Please note that more details on Earned Value will be discussed in our chapter notes on Project Cost Management.
Agreed with exerts answers....like @ Binil Paul , @ waseem Wali
Thanks
The EVM is commonly used method of performance measurement and integrates project scope,cost and schedule measure to help the project management team access project performance
EVM is performed on work packages and control account of WBS.
Earned value (EV) is the value of the work completed to date as it compares to the authorized budgeted amount assigned to the work component
Some benefits of calculating Earned Value in P6 are the ability to caluclate activity percent complete and view in graphical form to predict obstacles early in a project schedule; forecasting project progress more effectively; and developing an early understanding of progress according to budget and schedule to identify problems as they arise.
Actual Cost (ACWP) is the actual total cost incurred on the activity as of the project data date. ACWP is the same as the Actual Total Cost.
This is always the Total cost from the Baseline, calculated using the Baseline Budgeted Values or Baseline At Completion values depending upon the ‘Earned Value Calculation’ setting (Admin, Admin Preferences, Earned Value).
If the ‘Earned Value Calculation’ is set to ‘Budgeted Values with Planned dates’ or ‘Budgeted Values with Current Dates’:
If the ‘Earned Value Calculation’ is set to ‘At Completion Values with Current Dates’:
A CPI greater than 1 means that Earned Value is greater than the actual amount spent. A CPI of less than 1 means that the Earned Value is less than the actual amount spent.
Cost Variance is the difference between the Earned Value and the actual cost of that activity.
Earned Value Cost (EV) is the portion of the budgeted total cost of the activity that is actually completed as of the project data date. Also known as the Budgeted Cost of Work Performed for the activity. The method for computing the performance percent complete depends on the Earned Value technique selected for the activity’s WBS.
EAC is the estimated cost at completion for the activity.
Estimate to Complete is the estimated cost left to complete on the activity. The calculation can be customized at the WBS level (On the ‘Earned Value’ tab in the WBS view).
It can be computed as either:
Where ‘PF’ is a multiplier to weight the ETC calculation.This can be either ‘1’, ‘1/CPI’ or ‘1/(SPI * CPI)’ or user defined amount.
Planned Value Cost (PV) is the portion of the budgeted total cost of the activity that is scheduled to be completed as of the project data date according to the baseline dates. Also known as the Budgeted Cost of Work Scheduled for the activity. The Schedule % Complete specifies how much of the activity’s original duration has been completed so far based on the baseline dates.
A SPI greater than 1 means that Earned Value is greater than the Planned Value. A SPI of less than 1 means that the Earned Value is less than the Planned Value.