Register now or log in to join your professional community.
• Work packages: ◦ Are the work defined at the lowest level of the WBS for which cost and duration can be estimated and managed ◦ May be further decomposed into subproject work breakdown structure
• WBS dictionary: ◦ Provides detailed deliverable, activity, and scheduling information about each component in the WBS ◦ Supports the WBS
Good information about the Work Packages as the Lowest level of the Work Breakdown Structures. Thank and appreciating for your invitation and information.
Thanks
Appreciate your kind information
Apprciate positive approach ----------------------
thanks for the information
With greetings and appreciation
Thanks for the invitation. Well explained.
Thanks for your kind approach.
Good but there still is more to it & thanks for the invite.