Resource reallocation from non critical to critical activities is an example of which Project Scheduling technique?

 

A. Critical Path Method

B. Schedule Compression

C. Resource Leveling

D. What if Analysis

 

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/01/13
AMEER K m
by AMEER K m , civil engineer , BUILDERS GROUP

OPTION (C)..RESOURCE LEVELING. MAXIMUM RESOURCE SHOULD PROVIDE.

ZULFIQAR ALI
by ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology

My answer is 

C. Resource Levelling

 

DR MD ANWAR HOSSAIN
by DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you for invitation. My opinion is option C.

Noxolo Lewu
by Noxolo Lewu , Project Coordinator , Sanlam

The answer is resource levelling. The project manager wants to ensure that the project schedule reflects all those resource that are on a project's critical path.

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Of course it is C - resource leveling & thanks for the invitation. 

Muhammad Umar Farooq
by Muhammad Umar Farooq , IT Program Leader , Petro Rabigh

Schedule Compression, because activities are critical.

 

If resources were critical, it would be resource levelling.

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

I think option c because

Resource Leveling: Allocate scare resources to critical path activities first.

Abdul Rehman
by Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thank you for the invitation. My answer is B

Syed Kashif Abbas Jaffery
by Syed Kashif Abbas Jaffery , Business development and Capture Manager , LN Technology/ App maisters inc. USA

Answer is in question, it's A