Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Make payment to seller is done in?

 

A. Plan Procurements

B. Conduct Procurements

C. Administer Procurements

D. Close Procurements

user-image
Question added by Muhammad Farooq , QA-QC Manager , AL Bawani Contracting Co
Date Posted: 2017/01/21
Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Making final payment to seller is done in Close Procurement process. But progress based payment is done in Administer Procurement process.

hisham abu dagga
by hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

Thanks for invitation

Option C

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.