You are the project manager for Lucky Stars nightclubs. They specialize in live country and western band performances. Your newest project is in?

the Planning process group. You've published the scope statement and scope management plan. The document that describes who will receive copies of this information as well as future project information, how it should be distributed, and who will prepare it is which of the following?

A. Scope management plan

B. Project charter

C. Communications management plan

D. Information distribution plan

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/01/21
DR MD ANWAR HOSSAIN
by DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you for your invitation. I thing C. Communications management plan is good option.

hisham abu dagga
by hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

Thanks for invitation

option C

Abdul Rehman
by Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thank you for the invitation. My answer is C

mamoun mokhtar
by mamoun mokhtar , general manager , albyan technical foungary

it is i think option c can work here management communication plan

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Out of the given options , C - Communications Management is most appropriate.