Bar charts are most appropriate for?

 

A. Showing slack time.

B. Comparing actual to planned performance to each activity.

C. All of the other alternatives apply.

D. Showing critical path dependencies.

E. Showing which activities can be rearranged in parallel.

 

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/01/28
DR MD ANWAR HOSSAIN
by DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you for invitation. My answer is B. Comparing actual to planned performance to each activity..

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Answer is B - provided Baseline is set while scheduling the activities ; otherwise comparing actual to planned one is not possible.

Abdul Rehman
by Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thank you for the invitation. I would like to select B as my answer.

يوسف دمدوم
by يوسف دمدوم , مهندس و مسير , مقاولة اشغال البناء

Tink you for the invitation

My answer is for  option B

Thanks for the invitations.

 

My answer is Option B) Comparing actual....