A. Showing slack time.
B. Comparing actual to planned performance to each activity.
C. All of the other alternatives apply.
D. Showing critical path dependencies.
E. Showing which activities can be rearranged in parallel.
Thank you for invitation. My answer is B. Comparing actual to planned performance to each activity..
Answer is B - provided Baseline is set while scheduling the activities ; otherwise comparing actual to planned one is not possible.
Thank you for the invitation. I would like to select B as my answer.
Tink you for the invitation
My answer is for option B
My answer is for option (B)
Thanks for the invitations.
My answer is Option B) Comparing actual....