A non-critical path activity is completed in half the time. Then?

 

A. All of the other alternatives apply.

B. The slack in the path containing this activity will increase.

C. The total cost for this activity has decreased.

 

D. The critical path is also reduced.

 

E. Manpower from this activity can be assigned to other activities.

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/02/11
hisham abu dagga
by hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

__________Thank you for the invitation

Option B

_

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

In my opinion, The appropriate option is  B. The slack in the path containing this activity will increase.

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

In my opinion option E is most appropriate & thanks for the invite.

Sattar Abdulkarim  Mohamed
by Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

Appreciation for your invitation. It is Option B.

B. The slack in the path containing this activity will increase

DR MD ANWAR HOSSAIN
by DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you invitation.I seem option A. All of the other alternatives apply is good answer.

Abdul Rehman
by Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thank you for the invitation. My answer is B