stakeholders. What should you do next?
A. Develop the preliminary project scope statement.
B. Get the project charter signed.
C. Start to create project plan
D. Start the initial project planning process.
B - Get the project charter signed - C Start to create project plan.
Thank you for the invitation
Option D
It is B - Get the project charter signed and after this comes option A .
Appreciation for the invitation. My answer is Option D.
A. Develop the preliminary project scope statement.
Thank you for invitation. I seem option C. Start to create project plan is good answer.