additional resources should be assigned to:
A. All activities.
B. Those activities with the greatest degree of risk.
C. Those activities on the critical path beginning with the longest time duration activities.
D. Only those activities with the longest time durations.
E. None of the other alternatives apply
Thank you for the invitation
Option C
Thanks for the invitation. I would like to choose option C as my answer.
Actually Both B and C are correct. Critical Path activities have the greatest risk.
I shall choose C, because it is in detail that B.
To get more information on Project Management, follow the following page:
In my opinion - C. Those activities on the critical path beginning with the longest time duration activities.
My answer is for option B. Those activities with the greatest degree of risk.
Thank you for invitation. I seem C option appropriate.
It depends. Few of the activities may require additional resources to be deployed while few of them requires stretched targets. Either the case, the management decision shall be given with utmost priority and ensure no penalty payments become due or payable.