Register now or log in to join your professional community.
A. The customer will incur no further costs for the work the contractor performs in the completion of the contract.
B. The schedule and cost variance are zero.
C. The customer incurs the total financial responsibility for each additional dollar spent.
D. The contractor incurs the total financial responsibility for each dollar spent.
E. Both1) The contractor incurs the total financial responsibility for each dollar spent
, and2) The customer will incur no further costs for the work the contractor performs in the completion of the contract..
Thank you for the invitation. my answer is E
My answer is for option (E)
In my opinion - Option E --------------
Out of the given , option D is appropriate choice & thanks for the invite.
In reality PTA refers to " the amount above which seller bears all the loss of cost overrun " .