Register now or log in to join your professional community.
A. Noncritical path activities.
B. Critical pathactivites.
C. None of the other alternatives apply.
D. Slack time activities.
E. Dummies
Thank you for the invitation
Option E
C. Slack Time Activities as in Project Management the amount of time is called float or slack.
Option - B : Critical pathactivites.
Thank you for invitation. I seem option E. Dummies is good answer.
I will go with option C ; I do not think PMI uses the term dummies.
In my opinion - E. Dummies
----------- D. Slack time activities
they are called Slack Time Activities