Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Activities with zero time duration are referred to as?

 

A. Noncritical path activities.

B. Critical pathactivites.

C. None of the other alternatives apply.

D. Slack time activities.

E. Dummies

 

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/02/24
hisham abu dagga
by hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

Thank you for the invitation

 

Option E

 

C. Slack Time Activities as in Project Management the amount of time is called float or slack.

Nadjib RABAHI
by Nadjib RABAHI , Freelancer , My own account

Option - B :  Critical pathactivites.

 

DR MD ANWAR HOSSAIN
by DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you for invitation. I seem option E. Dummies is good answer.

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

I will go with option C ; I do not think PMI uses the term dummies.

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

In my opinion - E. Dummies

Sumaiyah Bhatti
by Sumaiyah Bhatti , Account Manager , ALTAVIA GROUP - MARKETING SERVICES PARTNER

they are called Slack Time Activities 

More Questions Like This