individual WBSs constructed. Which statement is not true regarding the subproject managers' WBS?
A. The work package level facilitates resource assignments.
B. The work package level defines the agreed-upon deliverables.
C. The work package level facilitates cost and time estimates.
D. The work package level is the lowest level in the WBS.
Answer is D. The work package level is the lowest level in the WBS. This statment is not true, as it can be lower.
Thank you for invitation. I think option B. The work package level defines the agreed-upon deliverables is good answer.
In my opinion
B. The work package level defines the agreed-upon deliverables.
It is option D of course & thanks for the invite.
A. The work package level facilitates resource assignments