What are the advantages of Primavera Over MS Project ?

user-image
Question added by Sowmya Priya Kumar , Planning Engineer , International Seaport Dredging Pvt Ltd
Date Posted: 2017/03/15
Nour Eldin Arafa  PMP
by Nour Eldin Arafa PMP , Project Manager , Isnad Egypt - The Group Company - Qatar

1-Primavera P6 Professional has a longest path critical activity     definition

2-Primavera P6 Professional has a feature, not found in Microsoft Project, called activity steps. This Primavera P6 steps feature provides two advantages

  1. It minimizes Gantt chart activity clutter
  2. It provides a discrete way of measuring schedule progress