Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

What percentage of activities is optimum for a longest path in a primavera baseline schedule ?

user-image
Question added by Binil Paul , Sr. Planning Engineer , KEO International Consultants
Date Posted: 2017/03/16
ZULFIQAR ALI
by ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology

It depends upon the level of schedule; if it is the very high level schedule then it is difficult to say what percent of activities should be on longest path.  However in my experience mostly between 10-15% of activities should be in longest path.

More Questions Like This