You are the project manager for Design Your Web Site, Inc. Your company is designing the website for a national grocery store chain?

 You have your activity list in hand and several alternative time estimates for each activity and are ready to diagram the activity dependencies. You should use which of the following?

A. PDM techniques

B. ADM techniques

C. PDM or ADM techniques

D. AON techniques

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/03/24
Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Today most network diagrams are created using option A - PDM technique. 

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

In my opinion - B. ADM techniques

hisham abu dagga
by hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

 

Thank you for the invitation

Thanks for the information 

 

I Agree Option B

DR MD ANWAR HOSSAIN
by DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you. Option C. PDM or ADM techniques.

---------  Option A. PDM techniques -------