Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

You are the project manager for the Heart of Texas casual clothing company. It's introducing a new line of clothing called Black Sheep Ranch Wear?

You will outsource the production of this clothing line to a vendor. Your legal department has recommended you use a contract that reimburses the seller's allowable costs and builds in a bonus based on performance criteria they've outlined in their memo. Which of the following contract types will you use?

A. CPPC

B. CPIF

C. CPF

D. CPFF

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/03/31
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: B

Explanation:

The cost plus incentive fee contract is one that the buyer reimburses the seller for the seller's

allowable costs and includes an incentive or bonus for exceeding the performance criteria laid out

in the contract.

Hussain  Alshagrawi
by Hussain Alshagrawi , Freelancer Consultant , Freelancer

I would prefer to use option (B)-CPIF which will have lower risk to seller provided that performance criteria will be acceptable and reasonable. 

Robert Malak
by Robert Malak , Projects Manager , Ankido Oil Services for General Contracts DMCC

 

I will follow Cost Plus Incentive Fee Contract (CPIF), because the risk is lower than the Cost Plus Fixed Fee (CPFF) and because the seller might artificially increase the cost to earn a higher profit in the Cost Plus Percentage of Cost (CPPC).

 

Saadi Abdallah Mohammad Abdel-Rahim Abdel-Rahim
by Saadi Abdallah Mohammad Abdel-Rahim Abdel-Rahim , Senior Logistics Officer , Oxfam GB

I'll have to take choice B, because it gives the seller more flexexibility and manuvaribility to do the best in marketing the product.

Nadeem Asghar
by Nadeem Asghar , Supply Chain Consultant/Trainer , Independent Practitioner

I would also go by CPPC, seems to be appropriate choice.

DR MD ANWAR HOSSAIN
by DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you for invitation. I think A. CPPC is good answer.

hisham abu dagga
by hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

Thank you for the invitation

Thanks for the information

 

Option B

 

Deleted user
by Deleted user

CPPC ,Although seller will have bit advantage to earn more profit by higher the price.

------------------ A. CPPC ----------------

Emmanuel Ozovehe
by Emmanuel Ozovehe , Head of Procurement and Operations , Alsaaz Int'l Ltd (Oil and Gas)

As a project manager, you are expected to do the followings:

1.   Write out the project statement of works (SOW): This is a document that: 

a.   Describe the objective of the project

b.   Defines the entire scope of the work to done for a vendor

c.   Clarifies deliverables (project milestones), progress report etc.

d.   Cost (Budget) 

e.   Proposed schedule, stating the commencement (Starting) and completion date of the project (Timeline)

f.    The resources needed for the project including facilities, equipment.

This document is then handed over to the vendor/supplier, who accept it as it is or modify and resubmit it back to the project procurement unit for ratification, acceptance or final approval.

Note that it is not always that the vendor or supplier will make input into an SOW. A times they might just accept the SOW as it is and work with it.

 

2.   Determine if you want to produce this new line of clothing in-house or you want to outsource.  If you favour outsourcing then you have to determine the payment structure that will suit the project such as; the cost plus incentive fee (CPIF), which reimburses the vendor or supplier for its allowable costs and also add performance reward for exceeding the criteria set out in the contract.  

Abdul Rehman
by Abdul Rehman , Electrical Engineer , Tamdeed Projects

Sorry, i have no knowledge about it.