A. Adding resource reserves to the activity resource estimates
B. Estimating by multiplying the quantity of work by productivity rate
C. Developing project schedule with contingency reserves as a recognition of the schedule risk
D. Incorporating time buffers into the activity duration estimates
Thanks for the invitation. My answer is D
Thank you for invitation. I think C. Developing project schedule with contingency reserves as a recognition of the schedule risk is good answer.
Thank you for the invitation
Thanks for the information
Option D
Thank you for the invitation
Iagree the option C.
C. Developing project schedule with contingency reserves as a recognition of the schedule risk
I will go with option - C & thanks for the invite.
Answer: D
Explanation:
Reserve Analysis ( Contingency ): Project teams may choose to incorporate an additional time
frame, called time reserve, contingency or buffer, that can be added to the activity duration or
elsewhere in the schedule as recognition of schedule risk.