You are the project manager working on a research project for a new drug treatment. Your preliminary project schedule runs past the due?

date for a federal grant application. The manager of the R&D department has agreed to release two resources to work on your project in order to meet the federal grant application date. This is an example of _.

A. adjusting the resource calendar

B. fast tracking

C. crashing

D. resource leveling

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/03/31
Abdul Rehman
by Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thanks for the invitation. My answer is C

DR MD ANWAR HOSSAIN
by DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you for invitation. I think appropriate answer is C. crashing.

Javad Taghavi
by Javad Taghavi , Program Manager, Senior Adviser in Project Management , KCE Co.

A should be correctg, because B & C are for compression schedule 

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Of course it is C - Crashing & thanks for the invite.