Which of the following is indicative of negative float?

 

A. The early finish date is equal to the late finish date.

B. The critical path supports the imposed end date.

C. The late start date is earlier than the early start date.

D. The project is sinking.

E. When leads are employed in the schedule.

 

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/04/07
Rajasekar Subramanian PMP MMUP Certified
by Rajasekar Subramanian PMP MMUP Certified , Sr.Planning Engineer , Al Darwish Engineering W L L

Option-C, The last Start date is earlier than the early Start date-  is correct answer 

DR MD ANWAR HOSSAIN
by DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you. My answer is Option C-The late start date is earlier than the early start date.

C. The late start date is earlier than the early start date