A. management reserve
B. cost budgeted for construction under water
C. forecasted budget over-runs
D. expended funds over which there is no further control
(D)
the costs that are out of control anymore and cant be recovered
sucking cost is the cost happened in the past and you have no control on it on the future
so i will go for D
In my opinion , option - D is most appropriate.
Thank you. I seem answer is D. expended funds over which there is no further control.
D. expended funds over which there is no further control