Can anyone please explain the responsibilities of quantity surveyor ?

user-image
Question added by Tobin absalone , design and estimation engineer , naffco
Date Posted: 2017/04/13
Mohamed Kamal
by Mohamed Kamal , Cost Control Manager , China State Construction Engineering Corporation Ltd. (Egypt)

quantity surveyor is the cost manager of a project responsible for all the related cost duties during the project life cycle ( Pre and Post contract phases) like cost planning and developing budgets , preparing BOQs, cost reporting and control, reporting on tenders, etc..

satish  venigalla
by satish venigalla , Contractor , Tecnicas Reunidas

prepare tender and contract documents, including bills of quantities with the architect and/or the client, undertake cost analysis for repair and maintenance project work.Advise on a procurement strategy. Identify, analyze and develop responses to commercial risk.

Preparation of BOQ, Invoicing, Takeoff, Subcontracting, Change Management (Claims Management). Upon completion of works and arrangement for payments. 

Baheerathan Irasamanikkam
by Baheerathan Irasamanikkam , Senior Quantity Surveyor , Alhamadi trading and Contracting

Procurement Routes

Forms of Contract

BOQ Preparation

Variation Evaluation

Valuation

Final Accounts

Contract Administration

Negotiation of Contracts

MOHAMED ARSATH NAZIR JAMAL
by MOHAMED ARSATH NAZIR JAMAL , Quantity Surveyor , ABV Rock Group of Companies

Quantity Surveyor roles and responsibilities are to study the Scope of work and contracts, Prepare Interim Payments and checking the every correspondence related like RFI, Letters, and instruction from engineer to check out whether the mentioned request have an additional cost impact or not 