Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Dummy relationships or dummy activities can be used in which Sequence Activities techniques?

A. Arrow Diagramming Method [ADM]

B. None of the other alternatives apply

C. Precedence Diagramming Method [PDM]

D. Fragment Network

user-image
Question added by Muhammad Farooq , QA-QC Manager , AL Bawani Contracting Co
Date Posted: 2017/04/14
hisham abu dagga
by hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

 

Thank you for the invitation

Thanks for the information 

 

I Agree Option A

Muhammad Farooq
by Muhammad Farooq , QA-QC Manager , AL Bawani Contracting Co

In my opinion - A. Arrow Diagramming Method [ADM]

DR MD ANWAR HOSSAIN
by DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you. I seem option A-Arrow Diagramming Method [ADM] is a good answer.

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

It is A - Arrow Diagramming Method which uses dummy activities to express logical relationship between activities & thanks for the invite.

Rajasekar Subramanian PMP MMUP Certified
by Rajasekar Subramanian PMP MMUP Certified , Sr.Planning Engineer , Al Darwish Engineering W L L

My Answer is C - Precedence Diagramming Method

Edgar Isaacs
by Edgar Isaacs , FIRE PREVENTION OFFICER , AFRAS

Arrow Diagramming Method [ADM]

andre andre
by andre andre , On Site Sitemanager/Structural /Civil/Mechanical/Tank plate Erection. , Kanye Kanye Projects Africa.

My awnser will be C -Relevant to the scope of work that is goint to be performed,

Abdul Rehman
by Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thank you for the invitation. My answer is C

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.