Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

If you are project manager, After a change request has been denied, you should?

A. Forget it

B. Record it and save it.

C. None of the other alternatives apply

D. Pass on to the project team.

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/04/20
Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Option - B , denied change request/s should be recorded & saved for future reference purpose.

Zaferullah Sharief, PMP®
by Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

All the rejected change request should be recorded and file/save it.  So the Option B is the correct choice.

More Questions Like This